We was asked by a client to visit a Food Processing Site in scunthorpe at night to , take a look at the feasability Of installing a slung scaffold

From the roof Trusses . Inside the Food Prep area we ascertained that we would require 750mm deep alloy beams to span the 6m gap Between the Main Steels,

I took a few pictures and measurements to give the scaffold designeer enough information to design the scaffold hangers required.

And Mentioned That we would have to use plastic / composite scaffold boards.